New Canal Steps

We are delighted to have completed the construction of the new canal steps which were opened for public use on Monday 5 March 2021. The new steps, which lead to the canal from Deepcut Bridge Road, have improved access to the canal and have an integrated bicycle rail which will help promote leisure and commuter cycle use of the towpath.

Working next to the canal, within a Site of Special Scientific Interest, posed many challenges. The canal is rich with wildlife and we had very stringent procedures to work around the canal, including environmental containment systems to prevent any contamination. To mitigate the risk, further precast concrete stair-units were used instead of using in-situ concrete.

A major logistical challenge for this work was to find a way to get the excavator onto the towpath to excavate and remove the old steps. The safest and most practical way was to engage a local Canal transportation company to deliver the 3.5 tonne excavator on a barge via Frimley Lock down to Deepcut Bridge Road.

This work was completed over a 17-week period and was carried out as part of the Section 106 planning obligations for the Mindenhurst development.

What else is on

Update on the new Food Store
10/05/2023
Update on the new Food Store
We are pleased to announce that we have just exchanged contracts with an...
May construction update
10/05/2023
May construction update
Click here for the latest construction news and progress at Mindenhurst
Following Carianne Blog
13/04/2023
Following Carianne Blog
This series is all about life as a Construction Manager, so I can tell you what my...

Sign up to our mailing list

Keep up to date with the latest news and events, as well as construction progress by signing up for our digital newsletter.