May construction update
1. Works are continuing on the Loop Road and Brunswick Road (on the barracks) where the team has been busy installing drainage,
building the new road, and creating new footpaths.
2. We will start to remove the scaffolding around St. Barbara’s Church once the external refurbishment and redecoration
works are complete. The team will begin decorating the South facing wall once the scaffolding has been removed as this area
is not accessible whilst the scaffolding is in place. We will then reinstall the church spire.
3. We will begin to create new footpaths in the Central SANGs – inside the fence line – and the Blackdown ANGST. There may be additional traffic around the Officers Mess on Blackdown Road to deliver the materials needed.
4. Highways improvement works will commence on the DIO Roads (Newfoundland, Union, and Canada Roads). This includes laying the foundation of the road, installing new surface water drainage and creating new footpaths. We will keep you informed of any work taking place around your home.
🌳 Landscaping maintenance works will continue to the Village Green, Mindenhurst Road and the Central SANGS.